Dhaka Sunday, December 22, 2024

Karnaphuli tunnel to be ready for traffic by 2022
  • Staff Correspondent
  • 2021-01-19 03:34:07

The 3.32-kilometre long tunnel under the Karnaphuli River is expected to be ready for vehicular movements by 2022.

"The overall progress of Karnaphuli Tunnel reaches 62 percent and the financial progress rose to 56.80 percent. Once completed, the tunnel will be a part of Asian Highway," Project Director (PD) Engineer Harunur Rashid Chowdhury told BSS on Monday.

He said the total length of the proposed first ever four-lane Bangabandhu Sheikh Mujibur Rahman tunnel will be around 9.39 kilometers, including 3.32 kilometers of the main tunnel, adding that the total length of the approach road between western and eastern side will be 5.35 kilometers alongside 727 meters of over bridge (Viaduct).

The project director said the length of tunnel tube will be 2.45-km, while 10.80 diameters inside the tube is fixed and vertical clearance inside the tunnel is 4.90 meters. According to the project details, 104 meters boring of the second tunnel tube has been completed so far till yesterday, while construction work of all 19,616 segments were completed in Zhenjiang city of Jiangsu province in China on December 31, 2020.

Besides, experts were making the segments rejected earlier there and 15,784 segments were brought in Chattogram site and 9,784 and 416 segments were installed in the under construction first tunnel and second tube respectively, it said.

Construction work of substructure for 727 meters viaduct was finished and superstructure work of 142 pre-febricated box girders out of 203 was ended.
Meanwhile, 115 pre-febricated box girders were installed in between 1-13 spans.

Harun-ur-Rashid hoped that the installations of rings in these tubes will be finished by next May or June, if weather remains favorable and no natural calamity takes place.

The two tubes comprised of four lanes and each tube measures 35 feet wide and 16 feet high. After completion of the project, it will greatly improve the traffic conditions in Chattogram and promote economic development of the country.

Earlier, Prime Minister Sheikh Hasina and President of China Xi Jinping laid foundation stone of the tunnel on October 14, 2017.

Later, Prime Minister Sheikh Hasina inaugurated the boring work of the tunnel on February 24, 2019.

The estimated cost of the tunnel is Taka 10,374.42 crores, where Chinese Exim Bank will provide 5,913.19 crores.

The Chinese firm, China Communication Construction Company Ltd (CCCC), was appointed as consultant for construction of the tunnel.

The tunnel will connect Chattogram Port and Anowara Upazila and is expected to make communication between Chittagong and Cox's Bazar easier with reducing traffic congestion on two bridges over the Karnaphuli River.

 

EC severs ties with Computer Council
Enforced Disappearances: Travel Ban and Passport Suspension for 20 Officials
Home Adviser Warns of Strict Action over Biswa Ijtema Killings