Dhaka Saturday, May 18, 2024

Production at Bangladesh’s lone coal mine to remain suspended
  • TFP Desk:
  • 2023-12-30 08:49:46

The production at the coal mine will resume within February after relocating all machinery in new phases, said deputy general manager of the coal mine, Rashed Kamal.


A total of 2.71 lakh metric tonnes of coal had been lifted under the current 1412 phase, and coal extraction under the 1209 phase would be resumed within February after maintenance work, he said.

The authorities concerned said some 1.95 lakh metric tonnes of coal were in stock for the Barapukuria Coal-fired Power Plant.

Abdullah Al Mamun, manager of the power plant, said there were three units of 525 MW capacity in the power plant, and there was enough coal to operate the power plant for two months.

Govt hikes gas price used in power production by Tk0.75 per cubic metre
Soybean oil has decreased by Tk 10 per litre
Bangladesh Economic Association proposes 70% tax on cigarettes, tobacco